File #: 24-183    Version: 1 Name:
Type: Informational Report Status: Filed
File created: 4/1/2024 In control: City Council Work Session
On agenda: Final action: 4/9/2024
Title: Request to approve settlement of Myers & Sons Construction, L.P. v. City of Colorado Springs, District Court, El Paso County, Colorado, Case No. 2020CV31791. Presenter: Wynetta Massey, City Attorney
Attachments: 1. Myers Case Summary (Mesa WTP)

 

Title

Request to approve settlement of Myers & Sons Construction, L.P. v. City of Colorado Springs, District Court, El Paso County, Colorado, Case No. 2020CV31791.

 

  Presenter: 

Wynetta Massey, City Attorney

 

Body

  Summary:

The City Attorney has negotiated a litigation settlement in excess of $100,000.00. Myers & Sons Construction, LP alleges that Colorado Springs Utilities breached a construction contract during the COVID pandemic. Colorado Springs Utilities countersued and filed a counterclaim for breach of contract against Myers & Sons.  The parties have reached a tentative settlement of the claim and counterclaim, subject to City Council approval pursuant to City Code section 1.5.506 (B).

 

 Background: 

The latest City Attorney quarterly report update on this case is attached.

  Previous Council Action:

N/A

 

  Financial Implications:

There are sufficient appropriated funds to pay this settlement.

 

  City Council Appointed Board/Commission/Committee Recommendation:

N/A

 

  Stakeholder Process:

N/A

 

  Alternatives:

N/A

 

Recommended Action

  Proposed Motion:

Move approval of the $10,000,000.00 settlement amount in Myers & Sons Construction, L.P. v. City of Colorado Springs, El Paso County, Colorado District Court Case No. 2020CV31791.

 

Summary of Ordinance Language

N/A